Project Overview:

MECO successfully executed a comprehensive upgrade to CEGCO’s fire safety infrastructure, ensuring enhanced protection and compliance with industry standards. The project scope included:


Transformer Protection: Replacement of deluge systems for transformers in Units 3, 4, and 5.

Fire Detection System Upgrade: Replacement of 10 local fire detection control panels and installation of a new master addressable fire detection control panel with an advanced graphic workstation.

Hydrant System Expansion: Installation of new fire hydrants to strengthen firefighting capabilities.

Hydrogen Plant Fire Protection: Installation of an automatic deluge system to safeguard the hydrogen generation plant.

Advanced UV/IR Detection Systems: Deployment of UV/IR detectors across multiple critical areas, including:

  1. Hydrogen detection system for the hydrogen generation plant.
  2. Fire detection for boilers’ burners in Units 1, 2, 3, 4, and 5.
  3. Fire protection for steam turbines in Units 1, 2, 3, 4, and 5.
  4. Gas safety monitoring at gas reducing stations in Units 1, 2, 3, 4, and 5.
  5. Fire detection solutions for chemical warehouses.
  6. Protection of the main HFO (Heavy Fuel Oil) tank.
  7. Safety measures for the HFO unloading area.
  8. Installation of a beam-type smoke detection system for warehouse fire safety.


Emergency Backup Power: Installation of an emergency diesel generator dedicated to the foam building for enhanced fire response capabilities. This project reflects MECO’s commitment to delivering cutting-edge fire safety solutions, ensuring operational safety, regulatory compliance, and asset protection for critical power generation facilities.